Pressure testing & test packages – planned, coordinated, documented

Pressure testing of piping is one of the largest work packages between the end of construction and commissioning. I split your piping systems into sensible test packages and manage the tests from preparation to release.

Request a project

Why test package planning drives the schedule

A new or revamped chemical plant often has several thousand metres of piping to test – with different piping classes, design pressures and materials. If test packages are defined too late or poorly, construction, insulation and commissioning end up waiting for each other. A well-thought-out split groups lines with the same test conditions, reduces the number of blinds and spades and makes progress measurable.

I bring together the perspectives of construction, commissioning and operations: the tests should not only be passed, but organised so that the plant can move on quickly to cleaning and commissioning.

Scope of services

  • Test package definition based on P&IDs, isometrics and piping classes
  • Test pressure, test medium (water or gas) and holding times according to applicable codes and site standards
  • Test package documents: mark-ups, test procedures, blind and spade lists, vent and drain points
  • Identification of components to be removed or isolated (e.g. valves, instruments, expansion joints)
  • Alignment with construction, owner and inspection bodies
  • Scheduling and progress tracking across all test packages
  • Test supervision, records and punch item tracking
  • Coordination of reinstatement and release after testing

How I work

  1. Review the basisCheck P&IDs, isometrics, piping classes, design data and site requirements.
  2. Define test packagesGroup lines with the same test conditions, set limits and isolation points.
  3. Prepare test documentsMark-ups, procedures and lists ready for construction to work with directly.
  4. Align and scheduleMatch the sequence with construction and commissioning plans, book inspection bodies.
  5. Support the testsAccept the preparation, supervise the test, record results and punch items.
  6. Reinstate and releaseRemove blinds, reinstall components, release the system for cleaning and leak testing.

Codes and framework

Test pressure, test medium and holding times follow the codes that apply to the plant – such as EN 13480 or AD 2000 – as well as German plant safety regulations and the owner's site standards. I align these requirements with everyone involved at an early stage, so there are no discussions at acceptance.

Result: fully tested and documented piping systems – and a schedule that construction and commissioning can rely on.