Service C

Leak testing – with the right test medium for every system

After pressure testing and cleaning, valves, instruments and gaskets are reinstalled. Before process media enter the plant, I make sure every joint is tight.

Request a project

Pressure testing is not leak testing

The pressure test proves the strength of the piping system – usually before blinds are removed and components reinstalled. Afterwards new joints are created: flanges are opened and closed again, instruments and valves are installed, gaskets are replaced. These are exactly the points a leak test checks, normally below the test pressure of the strength test.

Especially with flammable, toxic or environmentally hazardous media, a documented proof of tightness before first filling is a key safety step.

Medium-neutral planning

I am not tied to a particular test medium. The right medium depends on the system, the later operating medium, the required tightness, the owner's requirements and what is available on site – gaseous or liquid. I make this decision per test circuit and document it in a traceable way.

Methods

  • Pressure hold or pressure decay test – pressurise the system with the chosen test medium and monitor the pressure over a defined time
  • Leak detection spray / bubble test – targeted checks of flanges, fittings and reinstatement points with gaseous test media
  • Visual inspection – checking joints when liquid test media are used
  • Tracer gas and sniffer methods – where higher sensitivity or very small leak rates are required

Scope of services

  • Leak test planning: test circuits, test medium, test pressure, holding time and acceptance criteria
  • Register of all flanged joints and reinstatement points to be tested
  • Execution or supervision of pressure hold, visual, sniffer and leak detection tests
  • Follow-up and retesting of leaking points
  • Documentation and release of systems for commissioning

Safety during testing

Every test medium brings its own risks – stored energy under pressure, risk of asphyxiation with inert gases, release when depressurising. I therefore plan leak tests with clear isolation and venting routes, marked test areas and alignment with the owner's occupational safety team – so the test itself does not become a risk.

Result: a tight plant, a safe start, no surprises during start-up.